New Construction Calculator

Planning a spec home or a build on a lot? Enter what the finished house should sell for and what it will cost to build. The calculator works backward to the most you can pay for the lot and still hit your profit target, then shows the profit and cash needed at the seller's asking price.

Have the lot's address? CompDesk values the finished house from new-construction comps, builds the hard costs by phase or from your uploaded plans, and keeps the project timeline.

Your first lookup is free, with no account needed. A free account gets you 3 more.

Run a new-build pro forma

1 · The finished house

2 · Build costs

Hard costs: everything to build the house, including site work and the builder's markup if you use one. Soft costs: plans, engineering, permits, impact and tap fees, builder's risk insurance and utilities.

3 · The lot

4 · Construction loan and sale

Interest assumes the lot is financed at closing and construction draws average about 55% outstanding over the build, the same method CompDesk uses.

Max lot price—
Profit at asking price—
Cash needed—

Estimates for investment analysis. Get builder bids, check zoning and utility availability, and confirm loan terms before you buy a lot.

How a new construction pro forma works

With a flip, you start from the purchase price. With a new build, the lot price is the one number you can still negotiate, so builders work backward: start from what the finished house will sell for, take out every cost of building and selling it plus the profit you need, and whatever is left is the most the lot is worth to you. This is often called the residual land value method.

Max lot price ≈ projected sale price − target profit − hard costs − soft costs − contingency − financing − selling costs − lot closing costs

Financing depends on the lot price too, since a bigger lot means a bigger loan and more interest, so the calculator solves for the lot price exactly instead of subtracting a fixed number.

The five cost buckets

Worked example

A 2,100 sq ft spec house expected to sell for $525,000, built for $140 per sq ft, with a 7% contingency, soft costs of 10% of hard costs, an 80% construction loan at 10% and 10 months from lot purchase to sale. These are the numbers already in the calculator above.

Hard costs (2,100 sq ft × $140)$294,000
Contingency (7%) and soft costs (10%)$49,980
Selling costs (7% of the sale)$36,750
Target profit (15% of the sale)$78,750
Max lot price, after financing and closing costs$44,335

The seller is asking $50,000. At that price the profit drops to about $72,518, a 13.8% margin, and the project needs about $99,748 of your own cash. So the deal is close: offer near $44,000, find savings in the build, or accept a thinner margin.

Rules of thumb for new builds

Common new-build mistakes

Build the full pro forma

CompDesk's New Build tab prices hard costs by phase with installed line items, adds builder O&P and contingency, drafts a budget from your uploaded plans with AI Assistant, tracks project timing, and puts it all in a report for your lender.

New Construction Calculator questions

How do you calculate the max price to pay for a building lot?

Start with the projected sale price of the finished house. Subtract your target profit, hard costs, soft costs, contingency, construction financing, selling costs and lot closing costs. What's left is the most you can pay for the lot and still hit your profit target.

What is a new construction pro forma?

A pro forma is a projection of a project's costs, financing, timeline and profit before you commit. For a new build it covers land, hard costs, soft costs, contingency, the construction loan and selling costs against the expected sale price.

How much does it cost to build a house per square foot?

It depends heavily on the market, the size and the finish level. Get local builder bids for your plans; a per-square-foot number is useful for screening lots but not for a final budget.

What profit margin should a spec home builder target?

Many spec builders aim for a margin in the mid-teens or higher on the sale price, because new construction takes longer and carries more risk than a renovation. Thinner margins leave little room for delays or cost overruns.

What are soft costs in construction?

Soft costs are everything that isn't physical construction: architectural plans, engineering, surveys, permits, impact and utility tap fees, builder's risk insurance, and utilities during the build.